Tunnelling to restart on Sydney motorway, two years after sinkholes halt work

Contractors will restart work on a $3.2 billion motorway in Sydney after resolving a dispute with the NSW government. Construction halted for two years due to sinkholes, with the project now expected to be completed by 2029, four years later than initially planned. The consortium will not pursue additional costs related to the project.